D Morgan

News

PROPERTY TO LET - PRENTON24-May-2018

TO LET UNIT 1A & 1B (16 & 18) BADGER WAY NORTH CHESHIRE TRADING ESTATE PRENT..

Radio City Mission Christmas Toy Appeal14-Dec-2017

Every year, across Liverpool, Radio City holds Mission Christmas which raises awareness of..

  • Project: Littlewoods Site Development Enabling Works - Liverpool

  • Value: £40,000

  • Client: Littlewoods / Shop Direct

  • Role: Principal Contractor

  • Overview:

    Completion of 278 highway junction accessing proposed development site including drainage connections and provision for services

Scope of Works & Achievements

  • Installation of 18 kerbs to extend bell mouth
  • Widening of existing access & egress footpath
  • Excavate & backfill potholes on access road
  • Remove kerb tops from base units and remove from site.
  • Clean out base unit channel and dispose in bund.
  • Breakout existing base units, not compromising the existing bed.
  • Lift and string out base units ready for installing.
  • Place a mortar bed for the base units.
  • Use high strength mortar (weber.tec EP mortar) and install concrete channel tops.
  • Trim MOT ready to receive tarmac.
  • Clear Trees, hedges, and grass verge. Peel up existing footpath tarmac.
  • Hand dig service trenches.
  • Form service protection slabs.