  • Project: ROF Bishopton, Glasgow – Major Earthworks & Remediation

  • Value: £4.5m

  • Client: BAE Systems

  • Role: Principal Contractor

  • Overview:

    15 year project to regenerate a 2,000 acres former Royal Ordnance Factory site for housing, commercial and industrial purposes, providing a scenic and economic regeneration of the site

Scope of Works & Achievements

  • Excavating in the region of 4,000 tonnes per day
  • Excavation and Disposal of Hotspots
  • Remediation of the site wide contaminated hotspots
  • Grub Up and Process Foundations and Drainage 
  • Confidence Scrape
  • Cut & Fill to Design Profile
  • Construction of SUDS
  • construction of ponds and associated outfall drainage systems
  • Construction of headwalls to ponds, sediment forebays (concrete slab), permeable gabion basket berms and maintenance access tracks
  • Landfill Cell construction
  • Plant Management of Landfill Operations
  • Control of Borrow Pit Operations
  • Protection of Watercourses
  • Traffic & Materials Management
  • Avoided project delays via acceleration of work and successfully managing an extremely challenging physical environment