  • Project: M62 / M57 Junction 6 Improvements

  • Value: £2.1m

  • Client: Laing O’Rourke

  • Overview:

    Major earthworks scheme for new junction access and exit

Scope of Works

  • 500,000m3 of bulk excavation
  • Disposal of surplus Class 4
  • Removal of top soils and placement of fill of 430,000m3 to embankments and landscape areas, including re-soil and seeding
  • Provided plant and equipment to undertake the works in restricted areas of the site whilst working around the peak traffic issues

Achievements

  • Accommodated difficult live site environment & maintained output and programme following wettest summer on record
  • Reacted quickly to the better weather window and pulled back the earthworks programme to the delight of the client and Highways Agency 
  • Varied the material delivery and disposal to taking into account peak traffic times.