  • Project: Whiston Hospital

  • Value: £5m

  • Client: St Helens & Knowsley NHS Trust / Vinci

  • Overview:

    Major civils and infrastructure scheme, including demolition, earthworks, and groundworks

Scope of works included:

  • Demolition and dismantling of a former Victorian hospital building – within 6 metres of new ‘live’ hospital building
  • Several different building types to be demolished including, timber frame, concrete frame, portable frame and brick buildings
  • Several areas close to and joined to existing buildings not being demolished, which required special attention and the requirement for parts to be dismantled by hand
  • Drainage required the break out of existing concrete slabs, excavation of trenches, installation of pipes and manholes, backfill and reinstatement of concrete - within the confines of a building
  • Create new car parks for the hospital and demolish old car parks
  • Constructed new hospital access road, complete with continuation to public highway
  • Car park construction including extensive ducting, lighting columns and CCTV columns, and drainage
  • ACO kerbs and ACO drainage to install
  • Hard and soft landscaping – including main entrance