  • Project: Omega Phase 1 North - Infrastructure Works

  • Value: £4m

  • Client: Omega Warrington Ltd

  • Overview:

    Site Infrastructure and road construction, for a £1.25 billion mixed use development, 240 ha former Burtonwood US Air Force base

Scope of Works & Achievements

  • Site establishment and Site clearance Bulk earthworks
  • Traffic and materials management
  • Haul road to provide access to adjacent site
  • Spine Road Construction (including kerbs, gullies and manholes)
  • Improvement layer of formation (Import of sand fill / 1A granular fill from Bold Health - approx 10,000m³)
  • Blinding capping layer to protect formation (Import of 6F2 - approx 2,500m³)
  • Sub-base (Import of Type 1 MOT - approx 1,000m³)
  • Surface Course 50mm 8205m2, Binder Course 60mm 8218m2, Base Course 235mm 8230m²
  • Pedestrian and cycle lane construction (60mm binder, 20mm surface = 2560m²)
  • Extensive soft landscaping
  • Surface (approx. 280m of pipe runs) and Foul (approx. 600m of pipe runs) drainage installed
  • Drainage Swale and attenuation ponds
  • Foul pumping and foul water drainage station
  • Service crossings underneath M62 Motorway
  • Secondary Substation (500kv)
  • On-site services including mains electricity, gas, water and telecommunications