Central Rhyl Coastal Defences Scheme

Daniel Wilkinson • November 29, 2023

Project Update

Central Rhyl Coastal Defences Scheme

Working in collaboration with Balfour Beatty, this scheme is well underway with over 20,000 tonnes of rock placed and 1,000m3 of structural concrete poured so far.

The purpose of the scheme is to improve 2km of coastal flood defences in Central Rhyl to protect homes, businesses and the tourist economy from flooding events and coastal erosion well into the future.

The eastern section consists of 1 to 3 tonne rock scour protection to the foundations of the existing defences. The rock is mostly buried beneath the existing beach level and there will be new walkways constructed through the rocks to maintain beach access.

The western section consists of a new stepped revetment, raised and widened promenade and new seawall with improved access via steps and a ramp to the beach.

Works currently ongoing:
- Site clearance and demolition works
- Sheet piling installation to facilitate rock toe installation
- Rock toe installation
- Sheet pile installation for new revetment toe beam
- Revetment RC toe beam construction
- Revetment structural blinding mass fill works
- 6N placement and compaction for widening and raising the height of the existing promenade

A huge well done to the Balfour Beatty & D Morgan site team, specialist sub-contractors and the wider supply chain for the progress so far.

Working in collaboration with Balfour Beatty, this scheme is well underway with over 20,000 tonnes of rock placed and 1,000m3 of structural concrete poured so far.

The purpose of the scheme is to improve 2km of coastal flood defences in Central Rhyl to protect homes, businesses and the tourist economy from flooding events and coastal erosion well into the future.

The eastern section consists of 1 to 3 tonne rock scour protection to the foundations of the existing defences. The rock is mostly buried beneath the existing beach level and there will be new walkways constructed through the rocks to maintain beach access.

The western section consists of a new stepped revetment, raised and widened promenade and new seawall with improved access via steps and a ramp to the beach.

Works currently ongoing:
- Site clearance and demolition works
- Sheet piling installation to facilitate rock toe installation
- Rock toe installation
- Sheet pile installation for new revetment toe beam
- Revetment RC toe beam construction
- Revetment structural blinding mass fill works
- 6N placement and compaction for widening and raising the height of the existing promenade

A huge well done to the Balfour Beatty & D Morgan site team, specialist sub-contractors and the wider supply chain for the progress so far.

By Daniel Wilkinson October 20, 2025
Best Culture (Over 100 Employees)
By Daniel Wilkinson October 14, 2025
🎉Celebrating 75 Years of D Morgan plc & 50 Years of Leadership
By Daniel Wilkinson October 14, 2025
Opportunity to connect with emerging talent
By Daniel Wilkinson October 14, 2025
Opportunity to get hands-on
By Daniel Wilkinson October 14, 2025
Drone Pilot Academy Ltd
By Daniel Wilkinson October 14, 2025
At D Morgan, safety is more than compliance - it’s Our Culture.
By Daniel Wilkinson October 14, 2025
Team Visit
By Daniel Wilkinson October 14, 2025
Come and see us at Truckfest this weekend 🚛
By Daniel Wilkinson October 14, 2025
Montgomery Canal Restoration
By Daniel Wilkinson October 14, 2025
Training Together, Working Safer