2km of coastal flood defences in Central Rhyl to protect homes

The purpose of the scheme is to improve 2km of coastal flood defences in Central Rhyl to protect homes, businesses and the tourist economy from flooding events and coastal erosion well into the future.
The eastern section consists of 1 to 3 tonne rock scour protection to the foundations of the existing defences. The rock is mostly buried beneath the existing beach level and there will be new walkways constructed through the rocks to maintain beach access.
The western section consists of a new stepped revetment, raised and widened promenade and new seawall with improved access via steps and a ramp to the beach.
Progress to date:
▪️ Installation of 711no. PCC revetment units
▪️ Installation of 53no. PCC recurve wall facing panels
▪️ Installation of 19no. PCC anchor walls
▪️ Installation of 190no. PCC rear wave walls (with 6no more to go!)
▪️ Over 20,000t 6N structural fill placed to date
▪️ Rock toe and beach access stairs completed
▪️ Waterproofing works and lead flashing complete
▪️ Surface water drainage installation at 80% complete
Ongoing & scheduled works:
▪️ Ducting installation for street lighting
▪️ 200m3 foam concrete pours to various areas
▪️ MOT Type 1 import for upcoming surfacing visit in April
▪️ Construction of additional children's village and sky tower prom accesses
▪️ 2 new demountable flood barriers
▪️ Eastern ramp capping beam construction
▪️ 600m2 of insitu ramp slab construction
▪️ Placement of balance of rock armour to eastern ramp
A huge well done to the
Balfour Beatty plc &
D Morgan plc site team, specialist sub-contractors and the wider supply chain for the progress made to date.